They started a little later today and did mostly electrical. They were busy pulling wires and they moved the 220 amp outlet for the double oven. The plumber also came an rerouted the vent for the sink (I was incorrect in the copper pipe going through the soffit was not a drain, but a vent :) ). Here are a few pictures!
| On left is the 220 amp outlet for double oven and on right separate outlet for the refrigerator |
| My last minute addition -- an outlet right inside the door to the pantry for a cordless broom |
| Vent rerouted through the wall and ceiling. Code now requires PVC piping versus copper |
| Service switch next to the outlet for the garbage disposal required per code |
| Also, I primed a small area of the basement ceiling to see what it would look like painted white. Now to decide whether I want to tackle the whole area as it is a very messy job. |